Task

Progress

Project Date

Date Completed

Kickoff Call Completed 5/17/2019 5/17/2019
Development Website Sent Completed 6/4/2019 6/4/2019
Revisions Call Completed 6/10/2019 6/10/2019
Revisions Cutoff Scheduled 6/11/2019  
Revisions Complete      
Sent to QA      
Pre Activation Call      
Approval To Launch Given Requested 6/10/2019  
Activation Date/Dealer Access Scheduled Week of 6/10/2019  

 

Ready To Launch? Fill out this form.